Lake and Lathrop's last extension?

Board expresses impatience

Share on Facebook
Share on Twitter
Print

By ROBERT J. LIFKA

Despite opposition from one trustee and a threat from another to not support additional extensions, the River Forest Village Board granted extensions to the developer who plans to build a five-story, mixed-use property at the southwest corner of the intersection of Lake Street and Lathrop Avenue.

The major changes of the amendment give Lake Lathrop Partners LLC more time to submit a permit application, begin construction and complete the project due to delays involving the departure of Cigar Oasis from 7619 Lake St. Lake Lathrop Properties is a joint venture between Sedgwick Properties and Keystone Ventures. 

The village board voted 4-1 to approve an amendment to the agreement with Lake Lathrop Partners, with Trustee Patty Henek casting the negative vote and Trustee Respicio Vazquez recusing himself, citing a common-law conflict of interest since he works for the law firm that represents River Forest School District 90 and Oak Park and River Forest High School District 200. 

Under the amendment, the deadline for submitting the permit application has been changed from June 17, 2019, to Dec. 15, 2019; for beginning construction from Dec. 17, 2019, to May 1, 2020, or 30 days after the Illinois Environmental Protection Agency approves the remediation action plan for the project, whichever is later; and for completing the project from June 17, 2021, to Nov. 1, 2021. 

"It took a little while to get the tenants out," village President Cathy Adduci said in explaining the request for an extension and noting that the owners of Cigar Oasis had fought eviction efforts.

In response to a request from Henek for an update on the project, Mark McKinney, Sedgwick project manager, said plans are "evolving" but acknowledged they are not finalized.

He said soil borings for environmental purposes have been completed and additional soil borings to determine the capability of building support are under way. He added that commitments have been received from five prospective residents and cited "recent sales activity."

When asked by Henek about financing, McKinney said, "We're in that process." He noted an appraisal is required prior to financing, which he said his firm hopes to complete in November.

Outside the meeting, Cory Robertson, director of developer services for Jameson Sotheby's International Realty, real estate agent for the residential project, dismissed concerns that the project is on hold, as Henek implied while questioning McKinney.

Robertson said the temporary closing of the sales office for two weeks in late August and early September, which might have given that impression, was for personnel reasons and not an indication the project was on hold.

"The sales office is open now," he said. "For a couple of weeks we saw interested parties on an appointment basis while we were transitioning some of our people."

Marty Paris, Sedgwick president, also noted that the demolition process for this project is taking longer than similar demolition processes because the demolition firm is recycling a portion of the material.

Although he voted in favor of the amendment, Trustee Tom Cargie was critical of the delay.

"This is the last extension I will vote for," he said. "It seems like a continuous process of delays. There will be no more excuses moving forward."

Trustee Erika Bachner asked whether officials would terminate the agreement on the project if another extension is requested.

Adduci said she believed they would, adding "We have to get this done."

River Forest has committed $1.9 million in set-aside TIF funding for the development. If trustees vote to take back the property, then the village must reimburse the developer for demolition and environmental remediation costs. The developer previously estimated demolition at $250,000 and the village's environmental consultant estimated soil remediation at $1.2 million.

After the meeting Adduci expressed optimism the project would be completed but noted the "clawback" clause in the original contract that would allow the village to cancel the contract and name a new developer.

"It's going to work," she said. "I think our relationship is good. It took a while to get the tenants out."

She noted that the developer paid for demolition without outside financing and said she is "confident" that financing will be arranged. She also noted that soil remediation cannot begin until after all the material from the demolition is removed.

"We want it clean," she said.

Love the Journal?

Become our partner in independent community journalism

Thanks for turning to Wednesday Journal and RiverForest.com. We love our thousands of digital-only readers. Now though we're asking you to partner up in paying for our reporters and photographers who report this news. It had to happen, right?

On the plus side, we're giving you a simple way, and a better reason, to join in. We're now a non-profit -- Growing Community Media -- so your donation is tax deductible. And signing up for a monthly donation, or making a one-time donation, is fast and easy.

No threats from us. The news will be here. No paywalls or article countdowns. We're counting on an exquisite mix of civic enlightenment and mild shaming. Sort of like public radio.

Claim your bragging rights. Become a digital member.

Donate Now

Reader Comments

5 Comments - Add Your Comment

Note: This page requires you to login with Facebook to comment.

Comment Policy

Ed McDevitt from River Forest  

Posted: October 17th, 2019 12:37 PM

Let me add to my wife, Judith's comments. What a contrast: living next door to the Lake-Lathrop project site and reading of the River Forest Board's take on the current state of the project. Apparently, a Board majority willingly credits the assertion that construction hasn't started "due to delays involving the departure of Cigar Oasis from 7619 Lake St." The demolition of the existing building started at the corner of Lathrop and progressed to the cigar shop without noticeable delays and continued through the demolition of the cigar shop itself. Then everything stopped completely. Recyclean, the demolition company, ceased work weeks ago, took away their portapotty, as Judith noted, and left multiple pallets of sorted bricks, piles of unsorted bricks, a tangle of lumber, and a few pieces of equipment. They haven't been back either to reclaim their equipment or to restart work. It's clear that Recyclean is not being paid. In addition, developer Sedgwick's assertion that "soil borings" have been taken is quite suspect. We have seen no evidence that the area of the old parking lot has been drilled for "soil sampling." Possibly that happened before Recyclean enclosed the site and began demolition. It would be smart of the Board to require submission of the results of the alleged soil borings. It is disingenuous of Sedgwick to say that "plans are evolving" but "not finalized." The real estate agent can dismiss the idea that the project is on hold as much as he wants to. It's clear that current contractors are not being paid. The project is not just "on hold." It is at a standstill. No plan evolution is occurring. We who live next door look at that mess each day. The Village of River Forest needs to recognize that the developers are in real trouble and should be looking at how to clean up the eyesore at Lake and Lathrop. Just stop the nonsense and find a developer that can get actual financing and start construction. Ed McDevi

Anne Schmidt Dowling from River Forest  

Posted: October 17th, 2019 9:45 AM

Suggestion, Ask Marty Paris, President of Sedgwick, why his backyard deck has been under construction for years? This might be helpful in understanding the delays at Lake and Lathrop.

Bruce Kline  

Posted: October 16th, 2019 8:08 PM

I agree Judith. Despite all the official excuses, all objective signs point to a major problem. IMO, this project is dead.

Judith McDevitt  

Posted: October 16th, 2019 7:42 PM

Yes, delays may be common, but why hasn't Recyclean been on site for weeks? There are piles of rubble and recyclable materials yet to be processed as well as pallets of bricks packaged and ready to go. There's still one piece of equipment, but the Porta-Potty's been taken away. Are they coming back? I hope so before the snow flies.

Jolyn Crawford  

Posted: October 16th, 2019 5:42 PM

It's not unusual for construction delays, especially when eco friendly demolition and remediation need to take place.

Facebook Connect

Answer Book 2019

To view the full print edition of the Wednesday Journal 2019 Answer Book, please click here.

Quick Links

Sign-up to get the latest news updates for Oak Park and River Forest.


            
SubscribeClassified
MultimediaContact us
Submit Letter To The Editor
Place a Classified Ad

Latest Comments